Exhibit 02 · Published research lab

Grid Extreme Risk Toolkit

A forecast may be served only after it clears a pre-set calibration gate. Version 1.4 missed that gate, and the decision is published. The public Historical Lab uses 216 hours of ERCOT load. Official site: gertgrid.space. Tool: gert-d.vercel.app. Repository: DresdenGman/Grid-Extreme-Risk-Toolkit-GERT-.

ERCOT summer load curve, 2023-08-09 to 2023-08-11, against an assumed capacity of 80,000 MW
ERCOT summer load, 2023-08-09 to 2023-08-11 (72 hours), against an assumed available capacity of 80,000 MW: observed load above capacity for 21 hours; unserved-energy proxy 66,683 MWh. Project repository, docs/assets/load-curve.png. The capacity is an assumption, not a measurement.

The problem

Grids fail in the tail

A grid does not fail on the average day; it fails in the tail. GERT exists to make tail risk — and the model’s own untrustworthiness — visible at the same time, and to refuse service when the model has not earned it. The PJM cold-event benchmark, written out in the evidence below, asks the companion question: can interval calibration learned from past cold spells be transferred to the next one?

What I built

A gate the model cannot argue with

  • A FastAPI backend and a Next.js frontend. The current candidate, ercot-delta-quantile-v1.4, is a quantile model of load change. The calibration gate was written before the evaluation window was opened; a candidate that fails is not served — the forecast endpoint returns 503 — and the decision is published either way.
  • The public Historical Lab: 216 hours of measured ERCOT load in three 72-hour windows. Every result can be downloaded and independently recomputed; no account is required. Official site gertgrid.space; tool gert-d.vercel.app.
  • The PJM-Cold-Calibration-Benchmark: four extreme cold events, 3 model classes × 5 calibrators, each evaluated chronologically and by leave-one-event-out. The protocol is published in the benchmark’s preregistration/.

Evidence

What can be checked

  • v1.4 was not promoted. Against the pre-set gate of absolute coverage error ≤ 0.03, the recorded errors are Q90 0.035417, Q95 0.04375, Q99 0.031667. Source: decision record and the evidence JSON.
  • Skilled, and still rejected. Pinball skill against the frozen seasonal baseline ran +0.76 to +0.84 across quantiles. It did not buy promotion: the calibration gate is the decision, not the skill score. Source: the same decision record.
  • Historical Lab: 216 hours. In the summer-2023 window at an assumed 80,000 MW capacity, observed load exceeds capacity for 21 hours (66,683 MWh unserved-energy proxy); with a 5% load reduction, 7 hours and 4,458 MWh. Sources: dataset DOI 10.5281/zenodo.22975251 and the lab.
  • Tests: 142 backend and 51 frontend, passing on 2026-11-17 — the tool site’s own footer, gert-d.vercel.app. The earlier count, 141 backend and 50 frontend on 2026-11-09, is kept in the claim index.
  • Archives. Software: DOI 10.5281/zenodo.23982226 (v1.2.0, 2026-11-05). Dataset: DOI 10.5281/zenodo.22975251 (v1, 2026-09-26).
  • PJM cold-event benchmark. Day-ahead QR-GBT 90% interval coverage fell to 12.5% during the 2014 polar vortex, against 65.7% over the 2014 evaluation period; 0 of 18 repair cells passed. Retrospective leave-one-event-out evaluation overstates the Mondrian calibrators’ coverage by +11.6 and +21.2 percentage points against chronological evaluation. Sources: benchmark repository and DOI 10.5281/zenodo.24010850.
  • Two pilots are on record: Session 1 in May 2026 and Session 2 on 2026-09-08 (docs/FEEDBACK.md). No participant counts are published here: the figures in that document are organiser-reported and unverified, with no raw responses.
  • Community ledger: 4 organiser-forwarded reports, 2 hands-on core completions (self-reported), 0 independent retests (community page, updated 2026-09-25). A record of what happened — not adoption evidence.

Timeline

Public record only

  • 2026-02-10 — main repository created (GitHub record).
  • 2026-05 — Historical Lab Session 1 pilot (docs/FEEDBACK.md).
  • 2026-08-30 — v1.4 evidence published; the frozen evaluation window was 2026-08-21 to 2026-08-24 (96 hours).
  • 2026-09-08 — Session 2.
  • 2026-09-26 — dataset DOI published.
  • 2026-11-05 — software DOI, v1.2.0.
  • 2026-11-06 — PJM benchmark DOI.
  • 2026-11-17 — tool footer: 142 backend and 51 frontend tests passing.

Limits and next steps

What it cannot do yet

  • The v1.4 validation window is 96 hours — small for tail quantiles. The decision record states that this alone would not support promotion, independent of the gate result.
  • GERT is decision-support research, not an autonomous grid controller, and it is not deployed on an operating network.
  • The PJM benchmark has 1 submission; its git history cannot prove the preregistration predates the results, and the 2014 modelling table is not published with the repository.
  • A next candidate (v1.5) is pre-registered as a plan. It is not completed, and no result is claimed for it.

Media

Charts from the repository

Stylised gate chart: preregistered gate 0.030, with Q50 passing and Q90, Q95, Q99 failing
The gate, as the project draws it: preregistered gate 0.030; Q50 0.021 pass, Q90 0.035, Q95 0.044, Q99 0.032 fail — rejected, 1 of 4 passed. Project graphic (docs/assets/gate-chart.png); exact values are in the evidence JSON.
Pipeline graphic: recorded data, features, model, the gate, evidence
How a candidate earns the right to serve: recorded data, features, model, the gate, evidence. Project graphic (docs/assets/pipeline.png).

The lab, monitor and review screens can be used directly at gert-d.vercel.app; PJM figures on this page are drawn from the public benchmark repository, not from any private paper repository.